general approach:
TCK (Approach 1 SBOM) -> Company gets TCK -> performs test -> verification project gets result (Verified project trusts the results) -> further information still can be requested)
Step1 SBOM Check -> bare minimal for 1.0
Ensure that some mandatory S-CORE v1.0 (concrete list will be finalized in PR) modules are 100% included.
Take TCK to their repository.
Replace S-CORE modules with own modules.
Run SBOM generation.
Run test for SBOM which will be compared to S-CORE v1.0 S-BOM.
If there is a mismatch --> Feedback + negative result.
Step2 Test on Component Level - we should plan it, but maybe we will perform minimal test set on component level
20 PIT tests performed and passed
Step 3 (non mandatory)- In case of doubts we ask for a manual review
Agreed:
general approach:
TCK (Approach 1 SBOM) -> Company gets TCK -> performs test -> verification project gets result (Verified project trusts the results) -> further information still can be requested)
Step1 SBOM Check -> bare minimal for 1.0
Ensure that some mandatory S-CORE v1.0 (concrete list will be finalized in PR) modules are 100% included.
Take TCK to their repository.
Replace S-CORE modules with own modules.
Run SBOM generation.
Run test for SBOM which will be compared to S-CORE v1.0 S-BOM.
If there is a mismatch --> Feedback + negative result.
Step2 Test on Component Level - we should plan it, but maybe we will perform minimal test set on component level
20 PIT tests performed and passed
Step 3 (non mandatory)- In case of doubts we ask for a manual review
Activity
KaterynaKrykunova commentedon Nov 4, 2026
from: 4.11.2026
Participants: @b-rei @antonkri @KaterynaKrykunova @ansgarl @PiotrKorkus , Frank, Leonardo
Agreed:
general approach:
TCK (Approach 1 SBOM) -> Company gets TCK -> performs test -> verification project gets result (Verified project trusts the results) -> further information still can be requested)
Step1 SBOM Check -> bare minimal for 1.0
Ensure that some mandatory S-CORE v1.0 (concrete list will be finalized in PR) modules are 100% included.
e.g:
score_baselibs
score_communication
score_logging
score_lifecycle
score_persistency
score_time
• Check Company X's SBOM
Step2 Test on Component Level - we should plan it, but maybe we will perform minimal test set on component level
Step 3 (non mandatory)- In case of doubts we ask for a manual review
ToDos:
ansgarl commentedon Nov 4, 2026